About Project

Narrative description of Project:

Electra Water Authority intended to construct a complete new RO desalination system and utilities distribution system based on a turnkey contract for the Praia city. Works for the water treatment with a capacity of 5.000 m³/d, treating sea water, as specified in the Contract and which is reasonably required for the establishment on operable efficiency. The scope of the project was the basic-/ detailed engineering and supply of two skid mounted reverse osmosis system comprising: Well pumping station, SBS dosing station, automatic sand filters incl. backwash pumping and air scour blower station, Antiscalant dosing station, cartridge filters, high pressure pumping station incl.
energy recovery system by pressure exchanger (ERI), skid mounted reverse osmosis desalination system incl. CIP and flushing system, re-mineralization, post-disinfection- and pH adjustment dosing station, treated water tank incl. treated water pumping station, full set of instruments, complete set of analytical instruments, compressor station and service water pumping station, full set of laboratory equipment, electric LV panels, MCC, MCP, HMI/PLC incl. programming, erection, commissioning- and 2 years spares. to produce potable water.

Fields of Specialisation:

The Contractor had thoroughly to study the project, and also possess the necessary know-how technology, capability, skills, competence, experience also for local civil partner and provide qualified specialists in the field of potable water treatment for communities.

Description of actual services provided by staff within the assignment:

 Basic Engineering
 P&ID, PFD, Plant Layout incl. main equipment – 2D-3D
 Process Design and –Deskription
 Civil basic- and detailed design
 Equipment List
 Pipe List/- Valve List/- Instrument List/-Specification
 Power Consumption List
 Chemical Consumption List
 Delivery of mechanical/electrical equipment
 Supervision of erection
 Commissioning
 Project managementNarrative description of Project:
Electra Water Authority intended to construct a complete new RO desalination system and utilities distribution
system based on a turnkey contract for the Praia city. Works for the water treatment with a capacity of 5.000
m³/d, treating sea water, as specified in the Contract and which is reasonably required for the establishment
on operable efficiency.
The scope of the project was the basic-/ detailed engineering and supply of two skid mounted reverse osmosis
system comprising: Well pumping station, SBS dosing station, automatic sand filters incl. backwash pumping
and air scour blower station, Antiscalant dosing station, cartridge filters, high pressure pumping station incl.
energy recovery system by pressure exchanger (ERI), skid mounted reverse osmosis desalination system incl.
CIP and flushing system, re-mineralization, post-disinfection- and pH adjustment dosing station, treated water
tank incl. treated water pumping station, full set of instruments, complete set of analytical instruments,
compressor station and service water pumping station, full set of laboratory equipment, electric LV panels,
MCC, MCP, HMI/PLC incl. programming, erection, commissioning- and 2 years spares. to produce potable
water.
Fields of Specialisation:
The Contractor had thoroughly to study the project, and also possess the necessary know-how technology,
capability, skills, competence, experience also for local civil partner and provide qualified specialists in the field
of potable water treatment for communities.
Description of actual services provided by staff within the assignment:
 Basic Engineering
 P&ID, PFD, Plant Layout incl. main equipment – 2D-3D
 Process Design and –Deskription
 Civil basic- and detailed design
 Equipment List
 Pipe List/- Valve List/- Instrument List/-Specification
 Power Consumption List
 Chemical Consumption List
 Delivery of mechanical/electrical equipment
 Supervision of erection
 Commissioning